Install rain gutter on west side of main
Project No. 232Q8
Project Type: SHEET METAL / FENCING OAR: George Evans Program Type: K Status: FINALIZED
232Q8-1 :: Activity Schedule and Cost
Phase
Description
Start
Finish
% Complete
Current Budget
Planning
PLAN - Install rain gutter on west side of main bu
04/26/2004
A
04/30/2004
A
100 %
Construction
CONSTR - Install rain gutter on west side of main
07/12/2004
A
09/07/2004
A
100 %
$2,198
Close-Out
CLOSE-OUT - Install rain gutter on west side of ma
09/08/2004
A
09/30/2004
A
100 %
Subtotal for Segment 232Q8-1
$2,198
Project Total:
$2,198
Program Type:
ACE - Adult Career Education,
BB - Proposition BB,
COPS - Certificates of Participation,
CTE - Career Tech Education,
D_M - Deferred Maintenance,
ENV - Environmental,
ESCO - Energy Service Company,
FEMA - Federal Emergency Management Agency,
FIR - Fire Damage,
FSU - Proposition 1A and Measure Y,
K - Measure K,
MCD - Modified Consent Decree,
NTH - New Tech High,
QZAB - Qualified Zone Academy Bond,
R - Measure R,
RHU - Relocatable Housing Unit,
RRGM - Regular Routine & General Maintenance,
SM2 - State Match,
WIG - William Case Grant,
WLU - Waterless Urinals,
Y - Measure Y,
YBR - Measure Y Basic Repairs-Deferred