REPLACE SLABS, SIDEWALKS, STAIRS, STEM

Project No. 01055

Project Type: CONCRETE PAVING
OAR: Bernardo Sevilla
Program Type: BB
Status: FINALIZED
01055-1 :: Activity Schedule and Cost
Phase Description Start   Finish   % Complete Current Budget
Planning PLAN - REPLACE SLABS, SIDEWALKS, STAIRS, STEM 04/04/2005 A 04/30/2005 A 100 %
Design DESIGN - REPLACE SLABS, SIDEWALKS, STAIRS, STEM 05/03/2005 A 05/24/2005 A 100 % $5,258
Bid JOC Proposal - REPLACE SLAB, SIDEWALK, STAIR, STEM 10/13/2005 A 12/06/2005 A 100 % $0
Award JOC Proposal Acceptance - REPLACE SLAB, SIDEWALK 12/06/2005 A 12/19/2005 A 100 %
Construction CONSTR - REPLACE SLABS, SIDEWALKS, STAIRS, STEM 12/16/2005 A 08/17/2006 A 100 % $123,620
Close-Out Close Out LOE - REPLACE SLABS, SIDEWALKS, STAIRS, STEM 08/18/2006 A 02/21/2007 A 100 %
Subtotal for Segment 01055-1 $128,878


Project Total: $128,878
Program Type: ACE - Adult Career Education, BB - Proposition BB, COPS - Certificates of Participation, CTE - Career Tech Education, D_M - Deferred Maintenance, ENV - Environmental, ESCO - Energy Service Company, FEMA - Federal Emergency Management Agency, FIR - Fire Damage, FSU - Proposition 1A and Measure Y, K - Measure K, MCD - Modified Consent Decree, NTH - New Tech High, QZAB - Qualified Zone Academy Bond, R - Measure R, RHU - Relocatable Housing Unit, RRGM - Regular Routine & General Maintenance, SM2 - State Match, WIG - William Case Grant, WLU - Waterless Urinals, Y - Measure Y, YBR - Measure Y Basic Repairs-Deferred